Re: 2499 & 407 Intersection

Postby garyb66 » Tue Sep 28, 2010 10:06 pm

I use to read those dates on the FM site.. but usually they'd have a disclaimer stating TXDOT project and schedule.
garyb66
Old Timer
 
Posts: 122
Joined: Fri Aug 01, 2008 9:42 am
Location: Copper Canyon

Re: 2499 & 407 Intersection

Postby tech » Mon Oct 04, 2010 10:15 am

Does anybody know how they might tackle the remaining 2 phases, both scheduled to let July of next year? Will they go at the same time, or will one get prioritized over the other? For some reason I had it in my head that the stretch from Lantana Trail to Chinn Chapel was the last, but hopefully this isn't the case.
tech
Block Captain
 
Posts: 50
Joined: Fri Aug 27, 2010 10:38 am
Location: Lantana

Re: 2499 & 407 Intersection

Postby tech » Tue Nov 30, 2010 1:05 pm

So how are they going to complete this first phase by November 2011 with only 2 people working on the road at inconsistent times? I think one day a few weeks ago I might have seen a third person standing there with a shovel. How long should it seriously take to build the south shoulder up? More than a month? Because I think that’s where we are at this point.
tech
Block Captain
 
Posts: 50
Joined: Fri Aug 27, 2010 10:38 am
Location: Lantana

Re: 2499 & 407 Intersection

Postby garyb66 » Tue Nov 30, 2010 2:58 pm

Good question Tech.. I was wondering the same thing the other day. To me it sounds like a company that has bid and won more projects than they can handle, so they've got the minimal crew on site to at least meet some obligation that its being worked on and get paid by the state.
garyb66
Old Timer
 
Posts: 122
Joined: Fri Aug 01, 2008 9:42 am
Location: Copper Canyon

Re: 2499 & 407 Intersection

Postby Pipeline » Tue Nov 30, 2010 7:33 pm

tech wrote:So how are they going to complete this first phase by November 2011 with only 2 people working on the road at inconsistent times? I think one day a few weeks ago I might have seen a third person standing there with a shovel. How long should it seriously take to build the south shoulder up? More than a month? Because I think that’s where we are at this point.


Most of the electric lines are relocated. The gas lines have been relocated. The shoulder is now being raised to redo the drainage.No proper drainage, no road. It is all about DRAAAIIINAGE! (There Will Be Blood- dry movie)
"keep your powder dry people, Stormtroopers are coming, get ready"
Pipeline
King of the Block
 
Posts: 2234
Joined: Tue Feb 27, 2007 7:47 pm

Re: 2499 & 407 Intersection

Postby tech » Tue Nov 30, 2010 9:06 pm

I get what they are doing, just seems like they could maybe move a little faster with more than 2 people. Reminds me of the 3040 work several years ago.
tech
Block Captain
 
Posts: 50
Joined: Fri Aug 27, 2010 10:38 am
Location: Lantana

Re: 2499 & 407 Intersection

Postby JKTex » Wed Dec 01, 2010 11:21 am

tech wrote:I get what they are doing, just seems like they could maybe move a little faster with more than 2 people. Reminds me of the 3040 work several years ago.


Or 1171 now. But here's the kicker. In the case as I understand of 1171 (and likely other road projects in the area) the contractor has no incentive to move any faster than he needs to satisfy the contract completion date and terms. They use their crews where they need them to complete jobs that need to be completed. They may only have 1-2 people there because they have to work continually but have another job that completes sooner. As soon as they get to the point they need to get that one done, or have resources freed up, they'll show and and knock it out. If it were me, I'd do the same thing.

Utilization of labor and resources; it's how successful business's stay successful. If TxDOT or the county negotiated an early finish incentive/bonus, they'd have reason to over deliver. Without it, over delivering cost them money.
"We must reject the idea that every time a law's broken, society is guilty rather than the lawbreaker. It is time to restore the American precept that each individual is accountable for his actions." - Ronald Reagan
JKTex
King of the Block
 
Posts: 3710
Joined: Sat Jun 13, 2009 3:45 pm
Location: Flower Mound

Re: 2499 & 407 Intersection

Postby Uther » Wed Dec 01, 2010 1:06 pm

JKTex wrote:Or 1171 now.


This morning it took me 25 minutes (and I checked my clock) to drive westbound on 1171 between 2499 and Bruton Orand. For the life of me I couldn't figure out what the hold-up was. I felt for the car behind me. There were 2 school-age kids in there and I think they were trying to get to Liberty or Wellington. Damn near took my taillight out when they eventually got to Bruton Orand - but by then they were 10-15 minutes late anyways.
I finally found an avatar that works!
User avatar
Uther
King of the Block
 
Posts: 2228
Joined: Wed Jul 29, 2009 7:00 pm

Re: 2499 & 407 Intersection

Postby admin » Sun Jan 23, 2011 11:10 am

Update on FM 407 Reconstruction from the City of Highland Village:

Tiseo Paving began the TxDOT project to widen FM 407 from Briarhill Boulevard to west of Chinn Chapel Road in September. TxDOT has suspended all work by Tiseo Paving due to utility conflicts that have not been resolved. Currently TxDOT and Denton County Commissioner Bobbie Mitchell are working with franchise utilities and Bartonville Water Supply Company (BWSC), to relocate all infrastructure that is in conflict with the proposed reconstruction.  On November 1, 2010 work was suspended when the contractor hit the BWSC water line in the subgrade, which provides water service to an area of residents in the the Town of Flower Mound. The line needs to be relocated before construction can commence. It is anticipated construction will begin again in early February.
CrossTimbersGazette.com Admin
User avatar
admin
Site Admin
 
Posts: 9077
Joined: Fri Sep 09, 2005 10:29 pm
Location: Lantana

Re: 2499 & 407 Intersection

Postby skiing1974 » Tue Jan 25, 2011 3:39 pm

they had to start work, hit something they weren't supposed to, to find stuff underground! :lol:
User avatar
skiing1974
King of the Block
 
Posts: 2295
Joined: Sat Apr 29, 2006 11:21 am

Re: 2499 & 407 Intersection

Postby garyb66 » Wed Mar 02, 2011 9:16 pm

admin wrote:Update on FM 407 Reconstruction from the City of Highland Village:

Tiseo Paving began the TxDOT project to widen FM 407 from Briarhill Boulevard to west of Chinn Chapel Road in September. TxDOT has suspended all work by Tiseo Paving due to utility conflicts that have not been resolved. Currently TxDOT and Denton County Commissioner Bobbie Mitchell are working with franchise utilities and Bartonville Water Supply Company (BWSC), to relocate all infrastructure that is in conflict with the proposed reconstruction.  On November 1, 2010 work was suspended when the contractor hit the BWSC water line in the subgrade, which provides water service to an area of residents in the the Town of Flower Mound. The line needs to be relocated before construction can commence. It is anticipated construction will begin again in early February.


Now it's early March and no work has yet started....
garyb66
Old Timer
 
Posts: 122
Joined: Fri Aug 01, 2008 9:42 am
Location: Copper Canyon

Re: 2499 & 407 Intersection

Postby Uther » Wed Mar 02, 2011 10:26 pm

Well, this is TxDOT we're talking about. Have you been taking note of how long they've been delaying the 407/I35 intersection after they figured out that they could not build an underpass there? I don't have an engineering degree, but even I could tell them that an underpass in that low-lying spot was not going to work out.

Planning is not one of their strong points, IMNSHO.
I finally found an avatar that works!
User avatar
Uther
King of the Block
 
Posts: 2228
Joined: Wed Jul 29, 2009 7:00 pm

Re: 2499 & 407 Intersection

Postby admin » Wed Mar 02, 2011 10:28 pm

This just in from HV Mayor Scott McDearmont:

"Agreements on abandonment of the utility easements along FM 407 have been made. According to discussions at Monday's Precinct Three transportation meeting, the contractor will be back on the FM 407 project within the next seven to ten days."
CrossTimbersGazette.com Admin
User avatar
admin
Site Admin
 
Posts: 9077
Joined: Fri Sep 09, 2005 10:29 pm
Location: Lantana

Re: 2499 & 407 Intersection

Postby Brian » Mon Mar 07, 2011 12:30 pm

Whatever. 407 widening is about 5 years or more behind the infrastructure and population growth. We love the neighborhood but getting "trapped" in your area where it takes 20 minutes to get to a major highway is almost unacceptable. I am pretty sure I would have never moved here if I knew getting around would be so painful. Believe it or not but there is more to the DFW area the 4 corners of 407 and 2499.
Brian
King of the Block
 
Posts: 1251
Joined: Fri Sep 08, 2006 11:07 am
Location: Lantana

Re: 2499 & 407 Intersection

Postby garyb66 » Sat Apr 02, 2011 12:58 pm

admin wrote:This just in from HV Mayor Scott McDearmont:

"Agreements on abandonment of the utility easements along FM 407 have been made. According to discussions at Monday's Precinct Three transportation meeting, the contractor will be back on the FM 407 project within the next seven to ten days."


7 to 10 days LOL

It's now been 30 days.. I guess moving culvert pipes on scene counts as work.
garyb66
Old Timer
 
Posts: 122
Joined: Fri Aug 01, 2008 9:42 am
Location: Copper Canyon

PreviousNext

Return to Highland Village

Who is online

Users browsing this forum: No registered users and 1 guest

Powered by phpBB © 2000, 2002, 2005, 2007 phpBB Group